Penhall was contracted to provide specialized cutting and removal services for the concrete ballast wall located beneath the active light rail platform. Key elements of the project included:
Precision wall sawing to create controlled cuts
Test cuts and pressure relief cuts to support safe removal
Removal of approximately 185 linear feet of concrete wall
Coordinated work during limited access windows and a scheduled 48-hour shutdown
Efficient execution to meet demanding project timelines
PROJECT CHALLENGES & RESULTS
With no margin for error, this project required extensive planning and close coordination between day and night crews. Penhall crews worked four consecutive 12-hour shifts during the shutdown period to maximize productivity and ensure the work was completed on schedule.
Conducted multiple planning sessions before mobilization
Utilized separate day and night teams for continuous operations
Maintained strict safety standards throughout the project
Successfully completed the work within the shutdown window
Earned positive recognition from the City of Charlotte
Secured a verbal award for Phase 2 work based on project performance
EXECUTING WITHIN A 48-HOUR SHUTDOWN WINDOW
With train operations temporarily suspended, Penhall had a limited window to complete critical modifications beneath the active light rail platform. Success depended on extensive planning, around-the-clock coordination, and flawless execution.
Four consecutive 12-hour shifts to maximize productivity
Day and night crews working in coordinated succession
Multiple planning sessions prior to mobilization
Limited access windows with no margin for delays
Precision wall sawing performed beneath an active transit platform