CONCRETE CORING COMPANY
Demolition at 21st Ave Undercrossing
Penhall was contracted by Bridgeway Civil for the demolition of the 21st Ave bridge undercrossing on Hwy 99 in Sacramento, a high-profile infrastructure project. The process began with slotting the bridge deck and torching the rebar to expose the girders. Using boom lifts, a team secured rigging from a 550-ton crane while excavators broke the girder ends free. Once detached, the crane lifted each girder and placed it in a designated stockpile area for further removal.
Scope of Work:
This complex demolition required careful planning and expert coordination to ensure safe, efficient removal of the bridge components without disrupting the active highway.