PROJECT

710 Widening

Location: Los Angeles, California
Service: Flat Sawing, Core Drilling, Wall Sawing, Wire Sawing, Concrete Breaking, Concrete Removal, Bridge Demolition, Joint Sealing
Completion: September 2020

PROJECT HIGHLIGHTS

Penhall Company was hired to widen and seal isolation joins across seven bridges in East Los Angeles. This work included Hobart bridge 1,100’ long bridge over 18 RR tracks in BNSF yard mere feet away from new bridge. Washington bridge partial removal; three girders and deck, including wire saw/wall saw 4’ thick partial abutment removal. Work performed between the remaining existing bridge and new bridge. Bandini bridge work included selective cap removal of bent that was built at the wrong elevation saving column rebar. Widen and seal 34,000’ of isolation joint that competitor was unable to perform.

Equipment Used:

  • Flat saw
  • Core Drill
  • Wire Saw
  • Joint Seal Pump
  • Excavator
  • Compressor
  • Torch

Bandini bridge work included selective cap removal of bent that was built at the wrong elevation saving column rebar.

CONTACT US TODAY

"*" indicates required fields

Site Contact Information

(XXX) XXX-XXXX
 

Site Location

Location*

After submitting this form a Penhall Company representative will be in contact with you to confirm your request. If this request is urgent, please call 1-800-PENHALL to be connected with the nearest Penhall branch. Upon submitting this form you will also receive occasional updates about our services and company announcements. You may unsubscribe from these e-mails at anytime.

This field is for validation purposes and should be left unchanged.

OTHER ARTICLES

Penhall employees at site

What Do the Colors in Utility Marking Mean?

Penhall employees at site

The Difference Between Public and Private Utility Locating Services

Penhall employees at site

Post-Tension Cables: The Unsung Heroes of Modern Construction